1. This is considered as an external exposure... A. Production problems. B. Comp
ID: 427536 • Letter: 1
Question
1. This is considered as an external exposure...
A. Production problems.
B. Company management.
C. A change in demand of a product.
D. Organizational structure.
2. A problem in workflow is known as a...
A. A bottleneck.
B. Point of no return.
C. Stress point.
D. Non-accessible point.
3. An organization has faced a situation that caused all operations to halt until further notice. In crisis management what stakeholder should be notified of delivery of payment?
A. Employees.
B. Board of directors.
C. Suppliers.
D. Shareholders.
4. A local company gets all resources from one supplier to produce their product for the consumer market. There has been an opportunity to expand to others just in-case, but management is reluctant. Keeping their original supplier known as a...
A. Sole source supplier.
B. Single source supplier.
C. Comfortable with the apparent risk.
D. Crazy.
5. A consequence of machinery breakdown is...
A. Production may stall.
B. Suppliers.
C. Single source supplier.
D. Retaining of control.
What is the best answers for those qs
Explanation / Answer
C. A change in demand of a product
External exposure are the factors prevailing outside the organization which is not in control of the organization. Change in demand is not under control of a business.
2. A problem in workflow is known as a...
A , A bottleneck.
Bottleneck is the reason of adequate labour, resources and manpower to produce as much as demand in the market. Bottleneck occurs when demand exceeds the supply.
3 An organization has faced a situation that caused all operations to halt until further notice. In crisis management what stakeholder should be notified of delivery of payment?
A Employees.
Employees are very important to be informed for this purpose in case of crisis time.
4 A local company gets all resources from one supplier to produce their product for the consumer market. There has been an opportunity to expand to others just in-case, but management is reluctant. Keeping their original supplier known as a...
B Single source supplier.
There is a minor difference in sole and single supplier. Single source supplier meant for the supplier chosen among all alternative options. Sole supplier is the one where no option is available.
5 A consequence of machinery breakdown is...
A Production may stall.
It may cause delay in production which will deviate the output wanted.