Scope creep means:
    a. Needs emergence and identification
    b. Migration of project needs to requirements
    c. Uncontrolled changes to a project's requirements during project execution
    d. Imprecise scope statement

A tool that can show cost variance graphically is:
    a. A chart of accounts
    b. A code of accounts
    c. A histogram (also called a resource loading chart)
    d. A cumulative cost curve (also called S-curve)

A strength of the spiral model of the SDLC is that it reduces risk.
    a. true
    b. false

The following is used by systems analysts to capture dynamic processes:
    a. Standard flow chart analysis
    b. Context diagrams
    c. Process/Environment (P/E) diagram
    d. Decision tables

A review of a project's status indicates that BCWP = $400, ACWP = $400, and BCWS = $500. This indicates that the project is:
    a. On budget, behind schedule
    b. On budget, ahead of schedule
    c. Over budget, behind schedule
    d. Over budget, ahead of schedule Scope creep means:
    a. Needs emergence and identification
    b. Migration of project needs to requirements
    c. Uncontrolled changes to a project's requirements during project execution
    d. Imprecise scope statement

A tool that can show cost variance graphically is:
    a. A chart of accounts
    b. A code of accounts
    c. A histogram (also called a resource loading chart)
    d. A cumulative cost curve (also called S-curve)

A strength of the spiral model of the SDLC is that it reduces risk.
    a. true
    b. false

The following is used by systems analysts to capture dynamic processes:
    a. Standard flow chart analysis
    b. Context diagrams
    c. Process/Environment (P/E) diagram
    d. Decision tables

A review of a project's status indicates that BCWP = $400, ACWP = $400, and BCWS = $500. This indicates that the project is:
    a. On budget, behind schedule
    b. On budget, ahead of schedule
    c. Over budget, behind schedule
    d. Over budget, ahead of schedule

Explanation / Answer

1) Scope creeps: which is also termed as function creep/feature creep) refers to uncontrolled changes to a project's requirement during a project execution. It is considered as a risk in most of the projects.

2) A cumulative cost curve can be used to show cost variance graphically.

3) True spiral model strength is to reduce risk in SDLC even this approach is risk driven approach.

4) System analysts used process/environment diagram to capture dynamic processes.

5) Ob budget and ahead of schedule as budget and actual cost spent till date is less than budget cost for the plan scheduled.