AEC 258 Spring 2018 Assignment 4 (S0 points) Due date: 3/25/2018 1. Describe the

ID: 352673 • Letter: A

Question

AEC 258 Spring 2018 Assignment 4 (S0 points) Due date: 3/25/2018 1. Describe the four different solutions for a network. (10 points) 2. Describe four elements of project costs. (10 points) 3. What is time-cost trade-off? (10 points) 4. Figure out the least-time and least-cost schedule of the following project. Assume the indirect cost is $100 per day. (10 points) Activity # Time Time Crash Cost Normal Normal Crash Difference Difference S/day 100 200 400 100 500 560 200 260 250 200 520 270 70 1210 Cycle Activity to Can be NilDays Cost for Total shortened per day cycledirect cost duration cost Cost Project Total shorten shorten

Explanation / Answer

Question: Describe the four different solutions for a network.

The four different solutions for a project network are early start (ES), early finish (EF), late start (LS), and late finish (LF).

Early start for a an activity is found by moving forward through the project network from the Start activity along the longest time path to that activity and Latest finish from is time found by moving backward through the project network from the Finish node along the longest path to that activity.

Early finish is the early start plus the activity duration and late start is the late finish minus activity duration.