Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Moleno Company produces a single product and uses a standard cost system. The no

ID: 2490234 • Letter: M

Question

Moleno Company produces a single product and uses a standard cost system. The normal production volume is 120,000 units; each unit requires five direct labor hours at standard. Overhead is applied on the basis of direct labor hours. The budgeted overhead for the coming year is as follows:

During the year, Moleno produced 118,600 units, worked 592,300 direct labor hours, and incurred actual fixed overhead costs of $2,150,400 and actual variable overhead costs of $1,422,800.

Refer to the list below for the exact wording of a label or an amount description within your income statement.

Amount Descriptions

1. Calculate the standard fixed overhead rate and the standard variable overhead rate.

2. Compute the applied fixed overhead and the applied variable overhead. What is the total fixed overhead variance? Total variable overhead variance?

3. CONCEPTUAL CONNECTION Break down the total fixed overhead variance into a spending variance and a volume variance.

Fixed overhead analysis

4. CONCEPTUAL CONNECTION Compute the variable overhead spending and efficiency variances.

Variable overhead analysis

5. Journal entries for overhead variances were not discussed in this chapter. Typically, the overhead variance entries happen at the end of the year. Assume that applied fixed (variable) overhead is accumulated on the credit side of the fixed (variable) overhead control account. Actual fixed (variable) overhead costs are accumulated on the debit side of the respective control accounts. At the end of the year, the balance in each control account is the total fixed (variable) variance. Create accounts for each of the four overhead variances and close out the total variances to each of these four variance accounts. These four variance accounts are then usually closed to Cost of Goods Sold. Form a group with two to four other students, and prepare the journal entries that isolate the four variances. Finally, prepare the journal entries that close these variances to Cost of Goods Sold.

FOH $2,160,000* VOH 1,440,000 * At normal volume.

Explanation / Answer

1

Calculation of standard fixed overhead rate

Budgeted Fixed Overhead Cost (A)

$    2,160,000.00

Budgeted direct labor hours (DLH) (120000 units * 5 hours) (B)

600000

Standard Fixed Overhead Rate = A/B =

$                     3.60

Per DLH

2

Calculation of and the standard variable overhead rate:

Budgeted Variable Overhead Cost (A)

$    1,440,000.00

Budgeted direct labor hours (DLH) (120000 units * 5 hours) (B)

600000

Standard Variable Overhead Rate = A/B =

$                     2.40

Per DLH

3

Calculation of applied fixed overhead:

Actual Direct Labor hours worked (A)

592300

Standard Fixed Overhead Rate = (B)

$                     3.60

Per DLH

Applied fixed overhead =A*B =

$    2,132,280.00

4

Calculation of applied Variable overhead:

Actual Direct Labor hours worked (A)

592300

Standard Variable Overhead Rate = (B)

$                     2.40

Per DLH

Applied Variable overhead =A*B =

$    1,421,520.00

5

Calculation of Total Fixed overhead variance:

Actual Fixed overhead (A)

$    2,150,400.00

Applied Fixed overhead (B)

$    2,132,280.00

Total Fixed overhead variance = A-B =

$          18,120.00

U

6

Calculation of Total Variable overhead variance:

Actual Variable overhead (A)

$    1,422,800.00

Applied Variable overhead (B)

$    1,421,520.00

Total Fixed overhead variance = A-B =

$             1,280.00

U

1

Calculation of standard fixed overhead rate

Budgeted Fixed Overhead Cost (A)

$    2,160,000.00

Budgeted direct labor hours (DLH) (120000 units * 5 hours) (B)

600000

Standard Fixed Overhead Rate = A/B =

$                     3.60

Per DLH

2

Calculation of and the standard variable overhead rate:

Budgeted Variable Overhead Cost (A)

$    1,440,000.00

Budgeted direct labor hours (DLH) (120000 units * 5 hours) (B)

600000

Standard Variable Overhead Rate = A/B =

$                     2.40

Per DLH

3

Calculation of applied fixed overhead:

Actual Direct Labor hours worked (A)

592300

Standard Fixed Overhead Rate = (B)

$                     3.60

Per DLH

Applied fixed overhead =A*B =

$    2,132,280.00

4

Calculation of applied Variable overhead:

Actual Direct Labor hours worked (A)

592300

Standard Variable Overhead Rate = (B)

$                     2.40

Per DLH

Applied Variable overhead =A*B =

$    1,421,520.00

5

Calculation of Total Fixed overhead variance:

Actual Fixed overhead (A)

$    2,150,400.00

Applied Fixed overhead (B)

$    2,132,280.00

Total Fixed overhead variance = A-B =

$          18,120.00

U

6

Calculation of Total Variable overhead variance:

Actual Variable overhead (A)

$    1,422,800.00

Applied Variable overhead (B)

$    1,421,520.00

Total Fixed overhead variance = A-B =

$             1,280.00

U

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote