Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Seagren Industries Inc. manufactures in separate processes furniture for homes.

ID: 2465815 • Letter: S

Question

Seagren Industries Inc. manufactures in separate processes furniture for homes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows.

Cutting Department

Production Data—July

Plant 1
T12-Tables

Plant 2
C10-Chairs

Cost Data—July

Work in process, July 1

Materials

Labor

Overhead

   Total

SEAGREN INDUSTRIES INC.
Cutting Department—Plant 1
Production Cost Report
For the Month Ended July 31, 2014

Equivalent Units

Quantities

Physical
Units


Materials

Conversion
Costs

Units to be accounted for

   Work in process, July 1

   Started into production

      Total units

Units accounted for

   Transferred out

   Work in process, July 31

      Total units


Costs


Materials

Conversion
Costs


Total

Unit costs

   Total Costs

   Equivalent units

   Unit costs

Costs to be accounted for

   Work in process, July 1

   Started into production

      Total costs

Cost Reconciliation Schedule

Costs accounted for

   Transferred out

   Work in process, July 31

      Materials

      Conversion costs

   Total costs

Cutting Department

Production Data—July

Plant 1
T12-Tables

Plant 2
C10-Chairs

Work in process units, July 1 0 0 Units started into production 20,330 17,120 Work in process units, July 31 3,210 535 Work in process percent complete 60 80

Cost Data—July

Work in process, July 1

$0 $0

Materials

406,600 308,160

Labor

250,594 117,700

Overhead

111,280 103,469

   Total

$768,474 $529,329

Explanation / Answer

Solution :

SEAGREN INDUSTRIES INC.

Cutting Department—Plant 1

Production Cost Report

For the Month Ended July 31, 2014

Equivalent Units

Units to be accounted for

Physical Units

Materials

Conversion Costs

     Work in process, July 1

0

     Started into production

20330

         Total units

20330

Units accounted for

     Transferred out (20330-3210)

17120

17120

17120

     Work in process, July 31

3210

1926

1926

(3210*60%)

         Total units

20330

19046

19046

Costs

Materials

Conversion Costs

Total

Unit costs

     Costs in July

    406,600

                          361,874

       768,474

(250594+111280)

     Equivalent units

      19,046

                            19,046

          38,092

     Unit costs

         21.35

                               19.00

            40.35

Cost to be accounted for

     Work in process, July 1

                                      -  

                   -  

     Started into production

       768,474

         Total costs

       768,474

Cost Reconciliation Schedule

Costs accounted for

     Transferred out (17120*40.35)

       690,763

     Work in process, July 31

        Materials (1926*21.35)

                            41,117

        Conversion costs (1926*19)

                            36,594

          77,711

     Total costs

       768,474

SEAGREN INDUSTRIES INC.

Cutting Department—Plant 1

Production Cost Report

For the Month Ended July 31, 2014

Equivalent Units

Units to be accounted for

Physical Units

Materials

Conversion Costs

     Work in process, July 1

0

     Started into production

20330

         Total units

20330

Units accounted for

     Transferred out (20330-3210)

17120

17120

17120

     Work in process, July 31

3210

1926

1926

(3210*60%)

         Total units

20330

19046

19046

Costs

Materials

Conversion Costs

Total

Unit costs

     Costs in July

    406,600

                          361,874

       768,474

(250594+111280)

     Equivalent units

      19,046

                            19,046

          38,092

     Unit costs

         21.35

                               19.00

            40.35

Cost to be accounted for

     Work in process, July 1

                                      -  

                   -  

     Started into production

       768,474

         Total costs

       768,474

Cost Reconciliation Schedule

Costs accounted for

     Transferred out (17120*40.35)

       690,763

     Work in process, July 31

        Materials (1926*21.35)

                            41,117

        Conversion costs (1926*19)

                            36,594

          77,711

     Total costs

       768,474

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote