Problem 2: Supplier Selection (10 points)

Your sourcing department has received bids from three suppliers shown below.

PERFORMANCE DIMENSION

IMPORTANCE

Supplier 1

Supplier 2

Supplier 3

On Time Delivery (% on time)

0.50

97%

94%

88%

Excess Capacity (square feet of excess space)

0.40

11k sq. ft.

45k sq. ft.

80k sq. ft.

Cost ($/unit)

0.10

$3.50/unit

$3.75/unit

$2.55/unit

A) Score each supplier‘s bid using the following scale. (4 points)

On Time Delivery

Excess Capacity

Cost

Range

Score

Range

Score

Range

Score

<90%

1

<25k square feet

1

>$2.99 per unit

1

91%-93%

2

26k-35k square feet

2

$2.50-$2.98 per unit

2

94%-96%

3

36k-75k square feet

3

$2.25-$2.49 per unit

3

97%-98%

4

76k-125k square feet

4

$2.10-2.24 per unit

4

99%+

5

126k+ square feet

5

<$2.10 per unit

5

B) Calculate the weighted average score for each supplier. (4 points)

C )Which supplier should be selected based on these criteria? (2 points

PERFORMANCE DIMENSION

IMPORTANCE

Supplier 1

Supplier 2

Supplier 3

On Time Delivery (% on time)

0.50

97%

94%

88%

Excess Capacity (square feet of excess space)

0.40

11k sq. ft.

45k sq. ft.

80k sq. ft.

Cost ($/unit)

0.10

$3.50/unit

$3.75/unit

$2.55/unit

Explanation / Answer

(a)

(b)

(c)

Supplier 2 should be selected based on these criteria. It has high weighted score.

Importance Supplier 1 Supplier 2 Supplier 3 0.5 4 3 1 0.4 1 3 4 0.1 1 1 2