Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A single machine work center has five jobs assigned to it. They are labeled, in

ID: 403422 • Letter: A

Question

A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest (earliest) due date rule, what is the average completion (flow) time of all jobs?


A) 4.0
B) 12.6
C) 2.6

Explanation / Answer

Slack time for each activity = Due date time - time for processing the work

On the basis of slack time remaining , activities are sequenced as follows.

lateness for each activity is calculate as a difference of time to complete the activity and due date of that activity.

Average lateness = Total lateness / no. of activities = 15/5 = 3 days

Jobs Processing Time (days) Due Date Time (days) Slack time Remaining A 6 9 3 B 2 16 14 C 4 10 6 D 3 7 4 E 5 12 7
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote