Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Figure 8.26 Work-flow diagram for problems 4 and 5. 6. Determine the critical pa

ID: 380167 • Letter: F

Question

Figure 8.26 Work-flow diagram for problems 4 and 5. 6. Determine the critical path and the probability of completing the job of Figure 8.27 in 28 days. As in the preceding problems, the first number adjacent to each activity is the time in days and the second number is the standard deviation. Show the critical path. Determine the float, free float, independent float, and slack for activities and events in Figure 8.27. 7. L- Io, 2 6,1 28 6 3,1 3,7 12 7,2 4,1 L-1 Le21 Figure 8.27 Work-flow diagram for problems 6 and 7.

Explanation / Answer

Problem 1:

Path 1: ABDHI : Duration = 5+2+5+3+5 = 20

Path 2: ABEGI : Duration = 5+2+5+2+5 = 19

Path 3: ACFGI : Duration = 5+4+5+2+5 = 21

The project will take 21 days to complete

Critical path is ACFGI

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote