Figure 8.26 Work-flow diagram for problems 4 and 5. 6. Determine the critical pa
ID: 380167 • Letter: F
Question
Figure 8.26 Work-flow diagram for problems 4 and 5. 6. Determine the critical path and the probability of completing the job of Figure 8.27 in 28 days. As in the preceding problems, the first number adjacent to each activity is the time in days and the second number is the standard deviation. Show the critical path. Determine the float, free float, independent float, and slack for activities and events in Figure 8.27. 7. L- Io, 2 6,1 28 6 3,1 3,7 12 7,2 4,1 L-1 Le21 Figure 8.27 Work-flow diagram for problems 6 and 7.Explanation / Answer
Problem 1:
Path 1: ABDHI : Duration = 5+2+5+3+5 = 20
Path 2: ABEGI : Duration = 5+2+5+2+5 = 19
Path 3: ACFGI : Duration = 5+4+5+2+5 = 21
The project will take 21 days to complete
Critical path is ACFGI
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.