Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A small, privately owned Asian company is producing a private-label soft drink c

ID: 363048 • Letter: A

Question

A small, privately owned Asian company is producing a private-label soft drink called Yoggo. A bottling line puts the soft drinks into plastic bottles and then packages the bottles into boxes. The bottling line is comprised of the following four steps: (1) the bottling machine takes 1 second to fill a bottle, (2) the lid machine takes 3 seconds to cover the bottle with a lid, (3) a labeling machine takes 3 seconds per bottle, and (4) the packaging machine takes 4 seconds to place a bottle into a box. Problem data are summarized in the following table.

Process Step     Number of Machines     Seconds per Bottle

Bottling                        1                                  1

Apply a lid                    2                                  3

Labeling                       4                                  3

Packaging                    3                                  4

I What is the capacity (bottles/hour) at the resource “Apply a lid”?

II What is the bottleneck in the process?

III Assuming unlimited demand, what would be the flow rate

Iv Assuming unlimited demand, what would be the utilization at resource “Apply a lid”

v Assume the process started empty and that this is a machine-paced process. How long would it take to produce 500 bottles

VI If each machine is run by one worker, and each worker is paid $10/hour, then what is the cost of direct labor

VII What is the labor content?

VIII Assume that the demand rate is 5000 units/hour, what is the target manpower?

Explanation / Answer

Answer to question I :

Capacity at the resource “Apply a lid”

= 60 seconds/ 3 seconds per machine x 2 machines

= 40 machines

Answer to question II:

Bottles the bottling machine can produce in 1 minute using 1 machine

= 60 seconds/ 1 second per bottle

= 60 bottles

Total number of lids the 2 number of machines can apply in a minute

= 60 seconds/3 seconds    x 2 machines

= 40 numbers

Total number of labelling 4 number of machines can do in a minute

= 60 seconds /3 seconds x 4

= 80 numbers

Total number of packaging the 3 number of machines can do in a minute

= 3 x 60/4

= 45 numbers

Out of above, “apply a lid “ has the minimum capacity of 40 numbers per minute and hence should be considered as the BOTTLENECK process

Answer to question III:

Flow rate will be decided by the bottleneck process which is “Apply a Lid”

Since 40 number of lids can be applied a minute or 60 seconds,

Flow rate = 60 seconds/ 40 numbers = 1.5 second per lid

FLOW RATE = 1.5 SECONDS

Answer to question IV:

Utilization at “Apply a lid” which is the BOTTLENECK is 100 %

Answer to question V:

When the process starts empty , total time to fill the pipeline by the first unit

= 60/60 + 60/40 + 60/80 + 60/45 seconds    ( see answers to question 2 )

= 1 + 1.5 + 0.75 + 1.33 seconds

= 4.58 seconds

Flow rate = 1.5 seconds

Therefore , time taken to produce 500 bottles = 4.58 seconds + 1.5 x 500 seconds = 754.58 seconds

Answer to question VI :

There are toatl = 1 + 2 + 4 + 3 = 10 machines

And each machine is run by one worker

Therefore there are 10 workers

Each worker is paid $10/hour

Therefore, cost of direct labour = $100 per hour

Answer to question VII:

As has already been established , flow rate is 1.5 seconds per bottle.

Therefore, number of bottles it would process in 1 hour = 3600 seconds/ 1.5 second = 2400 numbers

Since direct labour cost = $100 per hour

It would cost $100 to produce 2400 number of bottles

Therefore labour content per item = $100/2400 = $0.04166

Answer to question VIII:

10 number of labor are required to produce 2400 number of bottles

Therefore, number of labor required to produce 5000 numbers = 5000/2400 x 10 = 20.83 ( 21 rounded to next higher number )

TARGET MANPOWER = 21

FLOW RATE = 1.5 SECONDS

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote