The partially completed inventory record for the driveshaft subassembly in the t

ID: 336255 • Letter: T

Question

The partially completed inventory record for the driveshaft subassembly in the table below shows gross? requirements, scheduled? receipts, lead? time, and current? on-hand inventory.

a. Complete the last three rows of the record for an FOQ of

50

units. ?(Enter your responses as integers. A response of? "0" is equivalent to being not? applicable.)

?Item: Driveshaft subassembly

FOQequals=50

Lead? Time: 3 weeks

Week

1

2

3

4

5

6

7

8

Gross

requirements

30

25

20

15

30

30

50

50

Scheduled

receipts

75

Projected? on-hand

inventory

10

Planned

receipts

b. Complete the last three rows of the record by using the L4L? lot-sizing rule.

c. Complete the last three rows of the record by using the POQ? lot-sizing rule, with

Pequals=4.

?Item: Driveshaft subassembly

Lot? Size:

FOQequals=50

units

Lead? Time: 3 weeks

Week

1

2

3

4

5

6

7

8

Gross

requirements

30

25

20

15

30

30

50

50

Scheduled

receipts

75

Projected? on-hand

inventory

10

Planned

receipts

b. Complete the last three rows of the record by using the L4L? lot-sizing rule.

c. Complete the last three rows of the record by using the POQ? lot-sizing rule, with

Pequals=4.

Explanation / Answer

Please find below filled up MRP table for both L4L as well as POQ rule.

For L4L:

Projected on hand inventory for period t = Projected on hand inventory for period t-1 + Scheduled receipt for period t – Gross requirement for period t( Provided Projected on hand inventory for period t > = 0)

In case Projected on hand inventory for period t <0as per above calculation , in such case:

Planned order receipt for period t = Gross requirement for period t – Scheduled receipt for period t – Projected on hand inventory for period t-1

Lot sizing rule = L4L

Driveshaft subassembly

1

2

3

4

5

6

7

8

Gross requirement

30

25

20

15

30

30

50

50

Scheduled receipt

75

0

0

0

0

0

0

0

Projected on hand inventory: 10

55

30

10

0

0

0

0

0

Planned order receipt

0

0

0

5

30

30

50

50

For POQ ( period order quantity ) = 4 :

Calculation for Projected on hand inventory for period t = same as above In case Projected on hand inventory for period t <0as per above calculation , in such case:

Planned order receipt for period t = Sum of gross requirements for periods ( t, t+1 , t+2 , t+3 ) – Scheduled receipt for period t – Projected on hand inventory for period t-1

Lot sizing rule =POQ of 4

Driveshaft subassembly

2

3

4

5

6

7

8

Gross requirement

30

25

20

15

30

30

50

50

Scheduled receipt

75

0

0

0

0

0

0

0

Projected on hand inventory: 10

50

30

10

110

80

50

0

0

Planned order receipt

0

0

0

115

0

0

0

50

Driveshaft subassembly

1

2

3

4

5

6

7

8

Gross requirement

30

25

20

15

30

30

50

50

Scheduled receipt

75

0

0

0

0

0

0

0

Projected on hand inventory: 10

55

30

10

0

0

0

0

0

Planned order receipt

0

0

0

5

30

30

50

50