1. Marcus and Tony work for Lombardo's Pipe and Concrete. Mr. Lombardo is preparing an estimate for a customer. He knows that Marco lays a slab of concrete in 6 hours. Tony lays the same size slab in 4 hours. If both work on the job and the cost of labor is $45.00 per hour, decide what the labor estimate should be.
2. A human factors expert recommends that there be at least 9 square feet of floor space in a college classroom for every student in the class. Find the minimum floor space that 40 students need.
Explanation / Answer
marcos rate of work = 1/6
tonys rate of work = 1/4
if they work together
1/6 + 1/4 = (4 + 6 )/24
= 10/24
so they will finish the work together in 24/10 hours
cost of labour = $ 45 / hour
so, labour estimate = 45 * 24/10
= $ 108