Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10

ID: 2797761 • Letter: C

Question

CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$350 $50 $50 $50 $210 $210 Project 2 -$650 $250 $250 $65 $65 $65

Which project would you recommend? Select the correct answer.

a. Both Projects 1 and 2, since both projects have IRR's > 0.

b. Neither Project 1 nor 2, since each project's NPV < 0.

c. Project 2, since the NPV2 > NPV1.

d. Both Projects 1 and 2, since both projects have NPV's > 0.

e. Project 1, since the NPV1 > NPV2.

Explanation / Answer

The Project to be selected to be the one with the higher NPV .

NPV of Project 1:

NPV of Project = Present Value of Cash Inflow - Present Value of cash Outflow

= $ 50 * 1/(1.10) ^ 1 + $ 50 * 1/(1.10) ^2 + $ 50 * 1/(1.10) ^3 + $ 210 * 1/(1.10) ^4 + $210* 1/(1.10) ^5 - $ 350

= $ 48.17

NPV of Project 2:

NPV of Project = Present Value of Cash Inflow - Present Value of cash Outflow

= $ 250 * 1/(1.10) ^ 1 + $ 250 * 1/(1.10) ^2 + $ 65 * 1/(1.10) ^3 + $ 65* 1/(1.10) ^4 + $65 * 1/(1.10) ^5 - $ 650

= - $ 82.52

Hence the correct answer is e. Project 1, since the NPV1 > NPV2

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote