A. Unitron Corp. is considering project Z, which costs $50 million and offers an
ID: 2765794 • Letter: A
Question
A. Unitron Corp. is considering project Z, which costs $50 million and offers an annual after-tax cash flow of $7.5 million in perpetuity. The project is in an industry that has greater market risk than Unitron’s typical projects. Unitron’s company weighted-average cost of capital, based on its typical projects, is 15%. Should Unitron Corp. accept project Z?
Yes, because the NPV of the project is positive.
No, because a zero-NPV project is a waste of resources.
Yes, because a zero-NPV project is marginally acceptable.
No, because the NPV of the project is negative.
Explanation / Answer
Yes, because a zero-NPV project is marginally acceptable.
Reason;
Cash flows in perpetuity is calculated as
=cash flows / cost of project
= $7.5/15%
=$50 million
In the given case , Npv = cash infow- cash outflow
= 50 - 50
=0 , zero Npv project.... it can be accepted as it is marginal. I.e at break even point of no profit no loss.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.