4. A firm is considering the purchase of an asset whose risk is greater than the
ID: 2763043 • Letter: 4
Question
4. A firm is considering the purchase of an asset whose risk is greater than the current risk of the firm, based on any method for assessing risk. In evaluating this asset, the decision maker should a. Increase the IRR of the asset to reflect the greater risk. b. Increase the NPV of the asset to reflect the greater risk. c. Reject the asset, since its acceptance would increase the risk of the firm. d. Ignore the risk differential if the asset to be accepted would comprise only a small fraction of the total assets of the firm. e. Increase the required rate of return used to evaluate the project to reflect the higher risk of the project.
Explanation / Answer
Answer-
e. Increase the required rate of return used to evaluate the project to reflect the higher risk of the project.