Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

For each of the problems listed, determine the following quantities for each act

ID: 2748456 • Letter: F

Question

For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and slack time. List the critical activities, and determine the expected duration of the project.

   
please complete this table with the information above

For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and slack time. List the critical activities, and determine the expected duration of the project.

Activity Immediate
Predecessor Estimated Time (days) A — 15                 B A 12                 C B 6                 D B 5                 E C 3                 F — 8                 G F 8                 H F 9                 I G 7                 J H 14                 K J 6                 End D, E, I, K   

   
please complete this table with the information above

  Activity     ES     EF    LF    LS     Slack A                B                C                E                D                F                G                I                H                J                K               

Explanation / Answer

  Activity Predecessor Time (days)     ES     EF    LF    LS     Slack A — 15 0 15 22 7 7 B A 12 15 27 34 22 7 C B 6 27 33 40 34 7 E B 5 27 32 43 38 11 D C 3 33 36 43 40 7 F — 8 0 8 8 0 0 G F 8 8 16 16 8 0 I F 9 8 17 43 34 26 H G 7 16 23 23 16 0 J H 14 23 37 37 23 0 K J 6 37 43 43 37 0