Dehner Corporation uses a job-order costing system with a single plantwide prede
ID: 2589622 • Letter: D
Question
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data Total direct labor-hours Total fixed manufacturing overhead cost Variable nanufacturing overhead per direct labor-hour 40,000 96,000 $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 755 $4,000 The predetermined overhead rate is closest to: $2.40 per direct labor-hour $3.00 per direct labor-hour $8.40 per direct labor-hour $5.40 per direct labor-hourExplanation / Answer
Solution:- $5.40 per direct labor-hour
Explanation:-
Please Rate or comment if you have any doubt regarding this solution.
Estimated Fxed manufacturing overhead $ 96,000 Estimated variable manufacturing overhead (40,000 * $3) $ 120,000 Estimated total manufacturing overhead cost $ 216,000 Divide by Estimated total machine-hours (MHs) 40,000 = Predetermined overhead rate $ 5.4Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.