Dehner Corporation uses a job-order costing system with a single plantwide prede
ID: 2605737 • Letter: D
Question
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour$ 6.80 67,000 $227,800 Recently, Job P951 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost 25 100 $ 660 $6,700 The total job cost for Job P951 is closest to: (Round your intermediate calculations to 2 decimal places.)Explanation / Answer
Predetermined overhead rate
= Budgeted overhead / Budgeted labor hours
= $227,800 / 67,000
= $3.4 per direct labor hour
Calculations
C – Variable overhead
= Variable overhead rate x Number of labor hours
= $6 x 100
= $600
D – Fixed overhead
= Fixed overhead rate x Number of labor hours
= $3.40 x 100
= $340
Calculations Particulars Amount $ A Direct materials 660 B Direct labor 6,700 C Variable overhead 600 D Fixed Overhead 340 E = Sum A to D Total Job Cost 8,300Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.