BLC has the tollowing intormation with respect to variable manufacturing overhea
ID: 2555805 • Letter: B
Question
BLC has the tollowing intormation with respect to variable manufacturing overhead for the month of June. The budget calls for 10,000 units to be produced using a total of 15,000 machine-hours. The variable overhead costs for the period are budgeted to be $180,000. During June, the actual output was 9,000 units. The total variable overhead costs were $171,000, and 14,000 machine-hours were actually used. BLC uses machine-hours to drive variable overhead What is the variable overhead spending variance for the month of June? $3,000 favorable $3,000 unfavorable S9,000 favorable $9,000 unfavorableExplanation / Answer
Answer : $3,000 unfavorable
Explanation :
Standard Rate = Budgeted variable overhead costs / Budgeted mahine hours
= $180,000 / 15,000 mahine hours = $12 per machine hour.
Variable Overhead Spending Variance
= Actual variable overhead cost - ( Standard Rate * Actual machine hours used)
= $171,000 - ( $12 * 14,000 hrs) = $171,000 - $168,000 = $3,000 unfavorable.
Note : Since actual variable cost is more than the total variable cost as per standard rate . thus the resultant Variable Overhead Spending Variance is unfavorable.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.