Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

BLC has the tollowing intormation with respect to variable manufacturing overhea

ID: 2555805 • Letter: B

Question

BLC has the tollowing intormation with respect to variable manufacturing overhead for the month of June. The budget calls for 10,000 units to be produced using a total of 15,000 machine-hours. The variable overhead costs for the period are budgeted to be $180,000. During June, the actual output was 9,000 units. The total variable overhead costs were $171,000, and 14,000 machine-hours were actually used. BLC uses machine-hours to drive variable overhead What is the variable overhead spending variance for the month of June? $3,000 favorable $3,000 unfavorable S9,000 favorable $9,000 unfavorable

Explanation / Answer

Answer : $3,000 unfavorable

Explanation :

Standard Rate = Budgeted variable overhead costs / Budgeted mahine hours

= $180,000 / 15,000 mahine hours = $12 per machine hour.

Variable Overhead Spending Variance

= Actual variable overhead cost - ( Standard Rate * Actual machine hours used)

= $171,000 - ( $12 * 14,000 hrs) = $171,000 - $168,000 = $3,000 unfavorable.

Note : Since actual variable cost is more than the total variable cost as per standard rate . thus the resultant Variable Overhead Spending Variance is unfavorable.