A CPA firm estimates that an audit will require the following work:
Type of Auditor Expected Hours Cost per Hour Standard Costs
Manager 10 $50 $ 500
Senior 20 40 800
Staff 40 30 1,200
Totals 70 $2,500
The actual hours and costs were:
Type of Auditor Actual Hours Actual Cost per Hour Actual Costs
Manager 9 $52 $ 468
Senior 22 38 836
Staff 44 30 1,320
Totals 75 $2,624
Required:
Calculate the direct labor, wage rate, and labor efficiency variances for each type of auditor and interpret.
Explanation / Answer
Hi,
Please find the answer as follows:
Part A:
Direct Labor Variance =Actual Labor Cost - Standard Labor Cost = 2624 - 2500 = 124 (Unfavorable)
Part B:
Wage Rate Variance = Actual Hours*(Actual Rate - Standard Rate)
Manager = 9*(52 - 50) = 18 (U)
+
Senior = 22*(38 - 40) = 44 (F)
+
Staff = 44*(30 - 30) = 0
Wage Rate Variance = 18 - 44 + 0 = 26 (Favorable)
Part C:
Efficiency Variance = Standard Rate*(Actual Hours - Standard Hours for Actual Production)
Manager = 50*(9 - 10) = 50 (F)
+
Senior = 40*(22 - 20) = 80 (U)
+
Staff = 30*(44 - 40) = 120 (U)
Efficiency Variance = -50 + 80 + 120 = 150 (Unfavorable)
Thanks.