A construction company began operations on January 2, 2010. During the year the

ID: 2490189 • Letter: A

Question

A construction company began operations on January 2, 2010. During the year the company was awarded three construction contracts. The company incurred $300,000 operating expenses for the year for which $275.0nn has been paid while the balance is owed as of December 31, 2010. Project data is summarized for each of the three projects in the following paragraphs. Project 101: Low-Rise Office Building The initial contract was signed on January 5, 2010 in the amount of S1,000,000 This amount included $300.000 tor construction costs, S150,000 for overhead mark-up, and $50,000 for profit markup. The contractor bro ground on February 4,2010. During the course of construction the client decided to upgrade the quality of th lighting and plumbing fixtures, resulting in a change order issued to the contractor in the amount of $100,000 on October 7, 2010. The change order price was calculated by the contractor as follows: $50,000 construction costs, $37,500 overhead markup, $12,500 profit markup. At the end of 2010, construction was not complete. However, the client was renting out office space to other entities as well as using some of the offices for the client's own business entity. Work remaining as of December 31, 2010 included surfacing the parking lot, erecting a portable parking attendant's station, miscellaneous site concrete work and landscaping. This work was schedule to be completed by May 1, 2010, weather permitting. A summary of accounting data as of December 31, 2010 included total construction costs in the amount of $800,000 for which $600,000 was paid. The balance reflected unpaid bills for the month of December, and retention withheld on subcontracts throughout the course of the project. The total progress billing as of December l, 2010 was $1,000,000 of which $900,000 was collected with the balance outstanding as retention receivable The project manager estimated that given the work left to be completed, approximately $200,000 of construction cost would be incurred. Project 102: Retaining Wall The initial contract was signed on October 17, 2010 in the amount of $100,000 The contract called for 1000 linear feet of 8 foot high retaining wall to be erected in a residential subdivision. Excavating and backfill was let to another contractor under separate contract. The estimator determined t foot for concrete, $10.00 per linear foot for reinforcing, and $50.00 per linear foot for labor. Average labor cost linear as $20.00 per hour. The hourly rate included insurances and fringes tied to labor. Overhead and profit markup were included in theše unit rates At the end of 2010 the project was not complete. The schedule indicates that backfilling of the wall would not occur until all wall installation work was complete. The project manager determined 780 linear feet of wall had been requiring an additional 450 labor hours installed and 2,150 labor hours were used. It was estimated it would take $30,000 to complete the project, records as of December 31, 2010 indicated that total expenditures to date were $80.000 of which Accounting $70,000 were paid. Progress billings to date were $85,000 and cash collected was $76,500

Explanation / Answer

5.

Project 102' Revenue = Total contract pricexPercentage of completion Percentage of completion = 1000000*73% = Cost incurred till date/estimated total cost =          730,000.00 = 80000/110000 = 73% Gross Profit = Estimated gross profit*Percentage of completion Estimated gross profit = (7,300.00) = Estimated revenue-Estimated cost = 100000-110000 = (10,000.00)
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote