Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

6) Prince Pots - Use the following information to answer the ensuing questions.

ID: 2484413 • Letter: 6

Question

6)  Prince Pots - Use the following information to answer the ensuing questions. Demand for pots is 26 pots a day. There are 260 working days in a year. It costs $65 to carry a pot in the warehouse over an entire year. Each order for pots cost $72. (a) Prince Pots is tooling around with a different idea of running a production facility to provide sheet metal for the pots. There are associated costs with running a production facility. Prince can produce 200 or less sheets of metal for $7 a piece. He can produce between 201 and 500 for $6 a sheet, and over 500 for $5 a sheet. How many sheets should Prince ask the production facility to produce in any given order? Interpret the costs for this EOQ. (b) Prince has found that the production facility can produce 35 sheets of metal a day. Assuming the demands given before part (a), how does the EOQ change from what is found in #5? Why did the EOQ change (in your own words)? (Part (a) has nothing to do with this question) 6)  Prince Pots - Use the following information to answer the ensuing questions. Demand for pots is 26 pots a day. There are 260 working days in a year. It costs $65 to carry a pot in the warehouse over an entire year. Each order for pots cost $72. (a) Prince Pots is tooling around with a different idea of running a production facility to provide sheet metal for the pots. There are associated costs with running a production facility. Prince can produce 200 or less sheets of metal for $7 a piece. He can produce between 201 and 500 for $6 a sheet, and over 500 for $5 a sheet. How many sheets should Prince ask the production facility to produce in any given order? Interpret the costs for this EOQ. (b) Prince has found that the production facility can produce 35 sheets of metal a day. Assuming the demands given before part (a), how does the EOQ change from what is found in #5? Why did the EOQ change (in your own words)? (Part (a) has nothing to do with this question)

Explanation / Answer

per day demand

26

no of working days

260

Annual demand

6760

carring cost

65 per pot per year

ordering cost

72 per order

EOQ= square root(2*Demand*cost per order/carrying cost per order)

       = SQRT(2*6720*72/65)

      = 122.0138706

Ordering cost= (6760/122.014)*72= 3989.0504

Carrying cost= (122.014/2)*65= 3965.455

Total = 7954.5054

Order quantity

Production cost

Ordering cost

Carrring cost

Total

            100

                                700

                              4,867

          3,250

          8,817

   122.014

                                854

                              3,989

          3,965

          8,809

            200

                            1,400

                              2,434

          6,500

       10,334

            300

                            1,800

                              1,622

          9,750

       13,172

            400

                            2,400

                              1,217

       13,000

       16,617

            500

                            3,000

                                  973

       16,250

       20,223

            600

                            3,000

                                  811

       19,500

       23,311

Answer a its best to order for 122.014 quantity

per day demand

26

no of working days

260

Annual demand

6760

carring cost

65 per pot per year

ordering cost

72 per order

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote