6) Prince Pots - Use the following information to answer the ensuing questions.
ID: 2484413 • Letter: 6
Question
6) Prince Pots - Use the following information to answer the ensuing questions. Demand for pots is 26 pots a day. There are 260 working days in a year. It costs $65 to carry a pot in the warehouse over an entire year. Each order for pots cost $72. (a) Prince Pots is tooling around with a different idea of running a production facility to provide sheet metal for the pots. There are associated costs with running a production facility. Prince can produce 200 or less sheets of metal for $7 a piece. He can produce between 201 and 500 for $6 a sheet, and over 500 for $5 a sheet. How many sheets should Prince ask the production facility to produce in any given order? Interpret the costs for this EOQ. (b) Prince has found that the production facility can produce 35 sheets of metal a day. Assuming the demands given before part (a), how does the EOQ change from what is found in #5? Why did the EOQ change (in your own words)? (Part (a) has nothing to do with this question) 6) Prince Pots - Use the following information to answer the ensuing questions. Demand for pots is 26 pots a day. There are 260 working days in a year. It costs $65 to carry a pot in the warehouse over an entire year. Each order for pots cost $72. (a) Prince Pots is tooling around with a different idea of running a production facility to provide sheet metal for the pots. There are associated costs with running a production facility. Prince can produce 200 or less sheets of metal for $7 a piece. He can produce between 201 and 500 for $6 a sheet, and over 500 for $5 a sheet. How many sheets should Prince ask the production facility to produce in any given order? Interpret the costs for this EOQ. (b) Prince has found that the production facility can produce 35 sheets of metal a day. Assuming the demands given before part (a), how does the EOQ change from what is found in #5? Why did the EOQ change (in your own words)? (Part (a) has nothing to do with this question)Explanation / Answer
per day demand
26
no of working days
260
Annual demand
6760
carring cost
65 per pot per year
ordering cost
72 per order
EOQ= square root(2*Demand*cost per order/carrying cost per order)
= SQRT(2*6720*72/65)
= 122.0138706
Ordering cost= (6760/122.014)*72= 3989.0504
Carrying cost= (122.014/2)*65= 3965.455
Total = 7954.5054
Order quantity
Production cost
Ordering cost
Carrring cost
Total
100
700
4,867
3,250
8,817
122.014
854
3,989
3,965
8,809
200
1,400
2,434
6,500
10,334
300
1,800
1,622
9,750
13,172
400
2,400
1,217
13,000
16,617
500
3,000
973
16,250
20,223
600
3,000
811
19,500
23,311
Answer a its best to order for 122.014 quantity
per day demand
26
no of working days
260
Annual demand
6760
carring cost
65 per pot per year
ordering cost
72 per order
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.