Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Need answer for the second paper Problem 6 (20 points) ards stand The Apoundrigh

ID: 2414241 • Letter: N

Question

Need answer for the second paper

Problem 6 (20 points) ards stand The Apoundright Company uses standard costing and has established the for its single product: Direct materials: 4 gallons at $8 per gallon Direct labor: 1.0 hours at 516 per hour Variable overhead: 0.5 hours at $8 per hour During November, the company made 6,000 units and incurred the followings Direct materials purchased: 26,800 gallons at $8.20 per gallon Direct materials used: 25,200 gallons Direct labor used: 5,600 hours at $15.30 per hour Actual variable overhead: $23,800 The company applies variable overhead to products on the basis of standard direct labor -hours. The materials price variance for November was: A. $5,360 F B, $5,360 U C. $5,040 F D. $5,040 U The materials quantity variance for November was: A. $22,960 U B. $22,400 U C. $9,600U D. $9,840 u AQ x AP AQ x SP (for qty) AQ x SP (for price) SQ x SP , Price Variance

Explanation / Answer

Answers

AQ

x

AP

AQ

x

SP

AQ

x

SP

SQ

x

SP

25200 gallons

x

8.2 per gallons

25200 gallons

x

8 per gallon

25200 gallons

x

8 per gallon

[6000 units x 4 gallons per unit] 24,000 gallons

x

8 per gallon

A

$    2,06,640.00

B

$         2,01,600.00

C

$             2,01,600.00

D

$ 1,92,000.00

Material Price variance = B - A

Material Quantity variance = D - C

$                                                                                                                                                                                                                                     (5,040.00)

$                                                                                                                                                                                                           (9,600.00)

Correct Answer: Option 'D' $ 5,040 Unfavourable

Correct Answer: Option 'C' $ 9,600 Unfavourable

AQ

x

AP

AQ

x

SP

AQ

x

SP

SQ

x

SP

5600 hours

x

15.3 per hour

5600 hours

x

16 per hour

5600 hours

x

16 per hour

[6000 units x 1 hour per unit] 6000 hours

x

16 per hour

A

$                85,680.00

B

$       89,600.00

C

$         89,600.00

D

$       96,000.00

Labor Rate variance = B - A

Labor Efficiency variance = D - C

$                                                                                                                                                               3,920.00

$                                                                                                                                              6,400.00

Correct Answer: Option 'D' $ 3,920 Favourable

Correct Answer: Option 'A' $ 6,400 Favourable

AQ

x

AP

AQ

x

SP

AQ

x

SP

SQ

x

SP

5600 hours

x

[23800/5600 hours] 4.25 per hour

5600 hours

x

8 per hour

5600 hours

x

8 per hour

[6000 units x 0.5 hour per unit] 3000 hours

x

8 per hour

A

$                23,800.00

B

$       44,800.00

C

$         44,800.00

D

$       24,000.00

Variable Overhead Rate variance = B - A

Variable Overhead Efficiency variance = D - C

$                                                                                                                                                             21,000.00

$                                                                                                                                         (20,800.00)

Variable Overhead Spending Variance = rate variance + efficiency variance = 21000 + (-20800) = $ 200 Favourable

Note: Variable Overhead Spending Variance = $ 200 Favourable, but there’s some mistake in Options available as $ 200 Unfavourable has been mentioned twice (Option A and Option C are same), while the correct answer $ 200 Favourable is not mentioned.

AQ

x

AP

AQ

x

SP

AQ

x

SP

SQ

x

SP

25200 gallons

x

8.2 per gallons

25200 gallons

x

8 per gallon

25200 gallons

x

8 per gallon

[6000 units x 4 gallons per unit] 24,000 gallons

x

8 per gallon

A

$    2,06,640.00

B

$         2,01,600.00

C

$             2,01,600.00

D

$ 1,92,000.00

Material Price variance = B - A

Material Quantity variance = D - C

$                                                                                                                                                                                                                                     (5,040.00)

$                                                                                                                                                                                                           (9,600.00)

Correct Answer: Option 'D' $ 5,040 Unfavourable

Correct Answer: Option 'C' $ 9,600 Unfavourable

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote