Figure 8-8 Rammazzotti, Inc., is looking for feedback on company performance. Th
ID: 2397896 • Letter: F
Question
Figure 8-8
Rammazzotti, Inc., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below:
Rammazzotti Inc., had the following budgeted data:
Unit sales for 2014 26,000
Unit production for 2014 26,000
Budgeted fixed overhead for 2014:
Supervision $ 800
Depreciation 2,000
Rent 100
Budgeted variable costs per unit:
Direct materials $0.15
Direct labor 0.20
Supplies 0.02
Indirect labor 0.05
Power 0.02
The following actually occurred:
Actual unit sales for 2014 24,000
Actual unit production for 2014 28,000
Actual fixed overhead for 2014:
Supervision $ 850
Depreciation 2,000
Rent 100
Actual variable costs:
Direct materials $3,500
Direct labor 4,900
Supplies 530
Indirect labor 1,250
Power 470
15. Refer to Figure 8-8. The budgeted cost for direct labor for 2014 was
a. $1,200.
b. $1,300.
c. $4,800.
d. $5,200.
18. Refer to Figure 8-8. The total flexible budgeted costs for 2014 are
a. $10,560.
b. $13,460.
c. $13,510.
d. $15,220.
20. Refer to Figure 8-8. The flexible budget variance for indirect labor for 2014 is
a. $1,250 F.
b. $50 F.
c. $150 F.
d. $1,200 U.
21. Refer to Figure 8-8. The flexible budget variance for total cost for 2014 is
a. $90 F.
b. $140 F.
c. $1,620 F.
d. $50 F.
22. Refer to Figure 8-8. The total actual costs for 2014 were
a. $13,550.
b. $10,650.
c. $13,600.
d. $13,510.
Explanation / Answer
answers
15. d $5200 (26000*0.20)
18.d $15220 (budgeted cost per unit * actual unit produced)
20. b $150F (1400-1250)
21.c $1620F (15220-13600)
22.c $13600
budget actual Unit sales for 2014 26,000.00 24,000.00 Unit production for 2014 26,000.00 28,000.00 fixed overhead for 2014: Supervision 800.00 850.00 Depreciation 2,000.00 2,000.00 Rent 100.00 100.00 Total Fixed Cost 2,900.00 2,950.00 variable costs per unit: Direct materials 0.15 4,200.00 3,500.00 Direct labor 0.20 5,600.00 4,900.00 Supplies 0.02 560.00 530.00 Indirect labor 0.05 1,400.00 1,250.00 Power 0.02 560.00 470.00 Total Variable Cost 12,320.00 10,650.00 Total Cost 15,220.00 13,600.00Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.