For the third quarter of the year, the following data was reported Inspection ti

ID: 2354570 • Letter: F

Question

For the third quarter of the year, the following data was reported Inspection time 1.4 days Process Time 4.5 days Wait time 12.0 days (the time between the customer order and the beginning of production) Queue Time 3.9 days Move time 0.8 days a. What is the throughput time? Show computations b. What is the manufacturing cycle efficiency for the quarter? Show computations c. What is the delivery cycle time? Show computations Read more: For the third quarter of the year, - JustAnswer http://www.justanswer.com/homework/58mi7-third-quarter-year.html#ixzz2AEwE7DBv

Explanation / Answer

A. Throughput time: 1.4 + 4.5 + 3.9 + 0.80 = 10.60 days B. MCE: 4.5/10.60 = 0.43 pr 43% C. Delivery cycle time = 10.60 days + 12.0 wait = 22.60 days

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote