Up, Up, and Away is a producer of kites and wind socks in Washington. Relevant data on the bottleneck operation in the shop for the upcoming fiscal year are given in the following table.
The shop works two shifts per day, 8 hours per shift, 190 days per year. Currently, the company operates four machines, and desires a 25 percent capacity cushion. How many machines should be purchased to meet the upcoming year's demand without resorting to any short-term capacity solutions?
The number of additional machines required is ??? (Enter your response rounded up to the next whole number.)
Item Kites Wind Socks Demand forecast 28,000 units/year 12,000 units/year Lot size 15 units 70 units Standard processing time 0.2 hour/unit 1.0 hour/unit Standard setup time 3.0 hours/lot 4.0 hours/lotExplanation / Answer
Shifts per day: 2
Hours per shift: 8 hours
Days: 190
Total number of hours available = N = Days x shifts/day x hours/shift
N = 190 x 2 x 8 = 3040 Hours
C = Desired capacity Cushion = 25%
Capacity requirement or number of machines (M) required is given as:
M =(Hours required by each product for processing and setup)/(Hours available per year after deducting desired capacity cushion)
M = [(Dipi + (Di/Qi)Si]/[N(1-C/100)]
Item
Kites
Wind Socks
Demand forecast
Dk = 28,000 units/year
Dw = 12,000 units/year
Lot size
Qk = 15 units
Qw = 70 units
Standard processing time
pk = 0.2 hour/unit
pw = 1.0 hour/unit
Standard setup time
Sk = 3.0 hours/lot
Sw = 4.0 hours/lot
Processing time required (Dipi)
28000 x 0.2 = 5600 hours
12,000 x 1.0 = 12,000 hours
Setup processing time required [(Di/Qi)Si]
(28000/15) x 3 = 5600 hours
(12000/70) x 4 = 685.7 hours
Total hours required for Processing and Setup
5600 +5600 = 11200 hours
12000+685.7 = 12685.7 hours
M = [11200 + 12685.7/[3040(1-25/100)]
M = 23885.7/2280
M = 10.48
11 Machines are required with a desired capacity cushion of 25 %.
The number of additional machines required is 11.
Item
Kites
Wind Socks
Demand forecast
Dk = 28,000 units/year
Dw = 12,000 units/year
Lot size
Qk = 15 units
Qw = 70 units
Standard processing time
pk = 0.2 hour/unit
pw = 1.0 hour/unit
Standard setup time
Sk = 3.0 hours/lot
Sw = 4.0 hours/lot
Processing time required (Dipi)
28000 x 0.2 = 5600 hours
12,000 x 1.0 = 12,000 hours
Setup processing time required [(Di/Qi)Si]
(28000/15) x 3 = 5600 hours
(12000/70) x 4 = 685.7 hours
Total hours required for Processing and Setup
5600 +5600 = 11200 hours
12000+685.7 = 12685.7 hours
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.