Francisco is planning a vacation to Germany. A variety of activities must be com
ID: 459629 • Letter: F
Question
Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:
Immediate
Activity Predecessors
A -
B -
C -
D A, B
E C
F D, E
G E
H F, G
I F
J I, H
Francisco was also able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5
Considering the information above, what is the slack for activities F and G respectively? (Points : 3) 0 days; 0 days
3 days; 0 days
4 days; 3 days
4 days; 0 days
Explanation / Answer
Activity Predecessor Activity Time ES EF LS LF Slack A None 3 0 3 1 4 1 B None 4 0 4 0 4 0 C None 5 0 5 0 5 0 D A,B 3 4 7 4 7 0 E C 2 5 7 5 7 0 F D,E 1 7 8 10 11 3 G E 4 7 11 7 11 0 H F,G 3 11 14 11 14 0 I F 2 8 10 12 14 4 J I,H 5 14 19 14 19 0 ES = E of Tail Event EF = ES + Activity Duration LF = L of Head Event LS = LF - Activity Duration Slack - LS - ES E = Earliest occurrence time for the event L = Latest allowable time for the occurrence of event Slack for activities F and G are 3 and 0 respectively. Hence the correct asnwer is Option B