Francisco is planning a vacation to Germany. A variety of activities must be com
ID: 459625 • Letter: F
Question
Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:
Immediate
Activity Predecessors
A -
B -
C -
D A, B
E C
F D, E
G E
H F, G
I F
J I, H
Francisco was also able to estimate the activity times as shown in the table below:
Activity Time (Days)
A 3
B 4
C 5
D 3
E 2
F 1
G 4
H 3
I 2
J 5
Considering the information above, what is the earliest finish time for activity E? (Points : 3) 5 days
6 days
7 days
8 days
Explanation / Answer
Activity E is preceded by activity C . The earliest start for activity E is the early finish of activity C . The early finish of activity C is 5 days . The early finish for activity E is = early start + activity time.
Early finish for activity E = 5 + 2
Early finish for activity E = 7 days .