Times (Days) Job Number Predecessor Jobs a m b 1 - 2 3 4 2 1 1 2 3 3 1 4 5 12 4
ID: 459409 • Letter: T
Question
Times (Days)
Job Number Predecessor Jobs a m b
1 - 2 3 4
2 1 1 2 3
3 1 4 5 12
4 1 3 4 11
5 2 1 3 5
6 3 1 2 3
7 4 1 8 9
8 5,6 2 4 6
9 8 2 4 12
10 7 3 4 5
11 9,10 5 7 8
a. Construct the appropriate network diagram
b. Indicate the critical path
c. What is the expected completion time for the project?
d. You can accomplish any one of the following at an additional cost of $1,500
(1) Reduce Job 5 by two days
2. Reduce Job 3 by two days
3. Reduce Job 7 by two days
If you will save $1,000 for each day that the earliest completion time is reduced, which action, if any, would you choose and why?
e. What is the probability that the project will be completed in 30 days?
Explanation / Answer
Total time taken by project - 25.83 days
Critical path - 1-4-7-10-11
a m b E Estimate 1 2 3 4 3 2 1 2 3 2 3 4 5 12 6 4 3 4 11 5 5 1 3 5 3 6 1 2 3 2 7 1 8 9 7 8 2 4 6 4 9 2 4 12 5 10 3 4 5 4 11 5 7 8 6.83Related Questions