What cycle time would match capacity and demand if demand is 113 units a day, th

ID: 455514 • Letter: W

Question

What cycle time would match capacity and demand if demand is 113 units a day, there are two shifts of 518 minutes each, and workers are given three half-hour breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.)


What cycle time would match capacity and demand if demand is 113 units a day, there are two shifts of 518 minutes each, and workers are given three half-hour breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.)

Explanation / Answer

Cycle time = 1/ throughput rate

=1/0.13

=7.69 minutes per cycle

Throughput rate = Unit produced /Time

=113 units/856 minutes

=0.13

Time =518 min - 90=428 min *2 shifts=856 minutes