What cycle time would match capacity and demand if demand is 122 units a day, th
ID: 443177 • Letter: W
Question
What cycle time would match capacity and demand if demand is 122 units a day, there are two shifts of 491 minutes each, and workers are given three half-hour breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.)
What cycle time would match capacity and demand if demand is 122 units a day, there are two shifts of 491 minutes each, and workers are given three half-hour breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.)
Explanation / Answer
Demand = 122 units per day
2 shifts of 491 minutes
Each workers is given 3 half hour break, one of which is for lunch or dinner
We need to substract the non production time: 90 minutes
491 - 90 minutes = 401 minutes x 2 shifts = 802 minutes per day
122 units = 862 / Cycle Time
Cycle Time = 862 / 122
Cycle Time = 7.06 minutes