Define Phase (Once you have found the correct answer, please show work) Six Sigm
ID: 453129 • Letter: D
Question
Define Phase (Once you have found the correct answer, please show work)
Six Sigma Projects project methodology normally begins with what initial step?
a. Problem definition
b. Define
c. Project Charter
d. Champion approval
A process consists of three sequential steps with the following yields:
Y1 = 99.8 Y2 = 97.4 Y3 = 96.4
Determine the total defects per unit
a. 0.063
b. 0.065
c. 0.067
d. 0.069
1000 units of products were examined for the possibility of 5 different undesirable characteristics. A total of 80 defects were found. How many defects would be expected in a million opportunities?
a. 16,000
b. 26,666
c. 61, 458
d. 80,000
The DPMO for a process is 860. What is the approximate Six Sigma level of the process?
a. 4.2
b. 4.4
c. 4.6
d. 4.8
In preparation of a project, efforts should be made to identify and involve various parties affected by the planned changes. These other parties are known as:
a. Process owners
b. Champions
c. Team leaders
d. Stakeholders
Explanation / Answer
Answer:
1. The initial step in any six sigma methodology is Define. However, since in this step be actually define the problem therefore Problem definition can also be correct answer in some peoples view. According to us the correct answer is Option b. Define.
2. Throughput Yield = e-DPU ; here, DPU is Defects Per Unit
Average Yield in the given question = 99.80 + 97.40 + 96.40 / 3 = 97.8667 therefore, 97.8667 = 2.71828-DPU or DPU =
3. Defects expected in 1 million opportunities = 80 x 1,000,000 / 1000 = 80,000; Correct answer is Option d.
4. The approximate Six Sigma Level of the process which has DPMO 860 is 4.60 approx. if 1.5 sigma shift over normal distribution is assumed.
5. These other parties are known as Stakeholders. Option d. is correct answer.