Multiple Choice: Select Best Single Answer. 19. W hich of the following processe
ID: 431883 • Letter: M
Question
Multiple Choice: Select Best Single Answer.19. W hich of the following processes include having team members provide time estimates for their activities and reaching agreement on the calendar date for each activity? a. Define Scope b. Sequence Activities c. Develop Schedule d. Develop Project Charter 20. Your project management plan results in a project schedule that is too long. If the project network diagram cannot change and you must meet the schedule but you have extra resources, what is the BEST thing to do? a. Level the resources b. Fast track the project c. Crash the project d. Perform a Monte Carlo analysis
Explanation / Answer
19 a) defone scope
20 a) level the resources
These are the correct option in this case if you think this helped do give a thumbs up else share your queries in comment section
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.