Multiple Choice: Select Best Single Answer.11. What is a recommended method for controling changes within a project? a. Have only the project manager able to initiate change b. Have each change approved or rejected by a board c. Allow each project member ultimate control of changes within their realm of the project without a review process d. Freeze scope and allow absolutely no changes 12. A process of iterative refinement of the project management plan as more detailed and/or accurate information becomes available is known as what? a. Progressive iteration b. Rolling wave planning c. Progressive elaboration d. Decomposition t is ready to accept the deliverables your project has produced. You should: Let go of the project resources and assign them to other projects. Refer to the quality plan to make sure the product meets specifications. a. c. Refer to the project management plan. d. Obtain client sign-off and follow administrative closure procedures
Explanation / Answer
11) All the changes required should flow through proper approval flow so as to check its real need and decide on best possible approach. Hence option B.
12) Continuous refinement of project plan to make it more accurate and precise is called Progressive iteration. Hence option A.
13) As the client has accepted the deliverables hence you should officially sign off and follow administrative closure procedures. Hence option D.