Previous Page Next Page Noter It is recommended that you save your response as you complete each question. Page 10 of 10 Question 10 (10 points) idl A vanilla shake machine requires a constant 2 minutes to make the special vanilla shake served at the Burger Shack. The machine can process one vanilla shake at a time. Requests for the special shake occur every 4 minutes, or 15 per hour on average. What is the average amount of time spent in the shake process. Ws (waiting and processing time)? A) 5 minutes B) 4.5 minutes c) 2 minutes D) 3.0 minutes Save Page 10 of 10 Previous Page

Explanation / Answer

Since, it is given that only 2 minutes are required to make the shake served at the Burger Shack and request comes every 4 minutes i.e. request time > making time

Therefore, the average amount of time spent in the shake process is 2 minutes as the customer will have to wait only for 2 minutes so that the shake gets prepared which is the processing time as well here.

So, here the option c. 2 minutes is correct (as per the given data interpretation)