End item Alpha\'s product structure tree and inventory information are as follow

ID: 419029 • Letter: E

Question

End item Alpha's product structure tree and inventory information are as follows: Alpha Alpha 2 0 4 15 3 30 3 30 1 10 2 30 1 100 H(3) M(2) P(2) W(2) S(2 B2) (4) S(2) All parts can be ordered using lot-for-lot ordering. (1) If 50 units of Alpha are to be assembled, how many additional units of S will be needed? (2) An order for 100 units of Alpha is scheduled to be shipped at the start of week 9. When is the earliest that any particular component must be started so that the order for Alpha will be ready to ship? Font familyFont size ParagraphHB (1) Additional units of S-800 (please include your computation in the answer. or upload an Excel file to indicate your Path: p

Explanation / Answer

1) 1 units of Alpha requires 1 unit of K & 2 units of M. 1 unit of K requires 2 units of S and 1 unit of M requires 2 units of S. Therefore, for 1 unit of Alpha we require 2+2*2 i.e 6 units of S. For 50 units of S, we shall require 300 units of S. As we already have 100 units of S in hand, the additional units of S requires is 300-100 i.e 200 units.

2) Lead Time of Alpha is 2 weeks, so order should be placed at start of 7th week

Lead Time of H is 4 weeks, so order should be placed at start of 3rd week

Lead Time of P is 1 week, so order should be placed at start of 2nd week

Lead Time of W is 2 weeks, so order should be placed at start of 1st week

Lead Time of K is 3 week, so order should be placed at start of 4th week

Lead Time of S is 1 week, so order should be placed at start of 3rd week

Lead Time of B is 1 week, so order should be placed at start of 3rdd week

Lead Time of M is 3 week, so order should be placed at start of 4th week

Lead Time of W is 2 week, so order should be placed at start of 2nd week

Lead Time of S is 1 week, so order should be placed at start of 3rd week

Therefore we can observe that component W needs to be order in the start of 1st week, so as to make the Alpha avaiable in the start of 9th week, and is one of the first components that needs to be ordered.

Please Like & Provide your reviews in comments. :-)