You are working on a project that has 12 activities. You determine that the crit

ID: 403419 • Letter: Y

Question

You are working on a project that has 12 activities. You determine that the critical path consists of only five activities. You then compute the variances for the five critical path activities and these variances are 3, 4, 2, 1, and 6 days. The desired completion date for the project is 44 days and the expected completion date for the project is 40 days. Which of the following alternatives gives the probability that the project will be completed by the desired completion date? You are working on a project that has 12 activities. You determine that the critical path consists of only five activities. You then compute the variances for the five critical path activities and these variances are 3, 4, 2, 1, and 6 days. The desired completion date for the project is 44 days and the expected completion date for the project is 40 days. Which of the following alternatives gives the probability that the project will be completed by the desired completion date? You are working on a project that has 12 activities. You determine that the critical path consists of only five activities. You then compute the variances for the five critical path activities and these variances are 3, 4, 2, 1, and 6 days. The desired completion date for the project is 44 days and the expected completion date for the project is 40 days. Which of the following alternatives gives the probability that the project will be completed by the desired completion date?

Explanation / Answer

answer is 0.91924

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote