Dave Fletcher was able to determine the activity times for constructing his lase
ID: 387360 • Letter: D
Question
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times Activity Time (weeks)Immediate Predecessor(s Activity Time (weeks) Immediate Predecessor(s) 8 C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF 10 Enter your answer in each of the answer boxes.Explanation / Answer
Slack = EF-ES
A=2,B=0,C=2,D=8,E=0,F=1,G=0,H=1
Critical Path=BEH
Total Project Completion Time= 20
ES EF A 0 5 B 0 7 C 5 7 D 5 8 E 7 10 F 7 14 G 10 21 H 14 20Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.