Dave Fletcher was able to determine the activity times for constructing his lase

ID: 387273 • Letter: D

Question

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:

1. Dave's earliest start (ES) and earliest finish (EF) are:

2. Dave's latest start (LS) and latest finish (LF) are:

3. The slack times are:

4. The activities on the critical path are

5. The total project completion time for Dave = ? weeks

activity time(weeks) immediate predecessor activity time(weeks) immediate predecessor A 7 -- E 3 B B 8 -- F 7 B C 2 A G 11 C,E D 2 A H 6 D, F

Explanation / Answer

From the precedence relationship, the possible paths and their corresponding durations as follows :

A-C-G = 7 + 2 + 11 = 20 weeks

B-E-G = 8 + 3 + 11 = 22 weeks

A-D-H = 7 + 2 + 6 = 15 weeks

B-F-H = 8 +7 + 6 = 21 weeks

4)Out of above, B-E-G is the critical path by virtue of having the longest duration

Activities on critical path are B, F, H

5) Project completion time will be same as duration of critical path. Therefore, project completion time will be 22 weeks

3)It is to be noted that Slack time of all activities lying on critical path are ZERO.

Therefore , slack time of activities B, E,G are ZERO

Slack time of activities F, H = Duration BEG – Duration BFH = 22 – 21 = 1 week

Slack time of activity A, C = Duration BEG – Duration ACG = 22 – 20 = 2 weeks

Slack time of activity D =Duration B-E-G – Duration ADH =21 – 15 = 6 weeks

Answer to questions 1 and 2 :

It is to be noted that :

Slack = Earliest Finish ( EF ) – Earliest Slack ( ES ) = Latest Finish ( LF ) - Latest slack ( LS )

Following table presents data on ES, EF, LS and LF

Activity

ES

LS

EF

LF

Slack

A

0

2

7

9

2

B

0

0

8

8

0

C

7

9

9

11

2

D

7

13

9

15

6

E

8

8

11

11

0

F

8

9

15

16

1

G

11

11

22

22

0

H

15

16

21

22

1

Activities on critical path are B, F, H