Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Q4b. Suppose you are the PM of a development project that is expected to be çeoa

ID: 383788 • Letter: Q

Question

Q4b. Suppose you are the PM of a development project that is expected to be çeoan years at a cost of $16,000 per month. After 9 months, you reali completed at a cost of $250,000. You are expected to conduct an eae.a ter months. Detemine view to ascertaining whether the project is on-time an and interpret the following: 3 ze that the ect is value analysis with a (3%) (a) Cost variation (CV) (b) Schedule variation (SV) (c) Cost performance index (CPI) (d) Schedule performance index (SPI (e) Estimate at completion (EAC) (D Estimated time to complete (ETC) (3%) (4%) (490) (3%) 3010

Explanation / Answer

From the scenario:

Budget at Completion (BAC) =$16,000*36 =$576,000

Actual Cost (AC) = $250,000

Planned Completion = 9/36= 25%

Actual Completion = 30%

Planned Value = Planned Completion (%) * BAC = 25% * $576,000 = $144,000

Earned Value = Actual Completion (%) * BAC = 30% * $576,000 = $172,800

Cost Variance = EV – AC = $172,800 - $250,000 = -$77,200

Schedule Variance = EV – PV = $172,800 - $144,000 = $28,800

Since Cost Variance is negative, this means the project is over-budget. Since Schedule Variance is positive, the project is ahead of schedule

Cost performance index = EV/AC =$172800 / $250000 =0.6912

It means , project is getting 69 cents from each dollar.

Schedule performance index =EV/PV = $172800 / $144000 =1.2

It means that the project is progressing with 1.2 time of the rate originally planned.

Estimate at completion =BAC/CPI =$576,000/0.6912 =$83333.33

So the total is not likely to be $83333.33

Estimate to complete=EAC-AC = $83333.33 -$250,000=-$166666.67

Thus project is expected to be over budget by $166666.67

I REQUEST YOU TO KINDLY RATE THE ANSWER AS THUMBS UP.