Moving to another queston wil save this response. own report saying "The project is still scheduled to be completed on time. Which of the following could be the reason the project manager made such a statement O The activity has a mandatory dependency, allowing the pro ect manager to place in the proiect shedule at any locatonthat he wants, to be done. Th. activity has tree noat and can be rescheduled later in its earlystart be latHnshindow. O The activity is on the critical path but is to be done after another activity that does have float O The activity is on a near-critical path with less float than the length of the delay US 12/140 ere to End Home 7 CaExplanation / Answer
The activity has free float and can be rescheduled in its early start to late finish window
Note: Please make sure the questions that you post are readable. I believe to the best of my understanding of the question (as many words were not visible), that this is the correct answer.
The activity cannot be started to date still the project is not delayed because the activity has a free float which thus does not pose a constraint to the completion of the project.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.