Moving to another question will save this response. Question 10 of 25 estion 10 2 points Save Ans It is week 1 and there are currently 50 items in stock We need 300 items at the start of week 5, If there are scheduled receipts planned for week 3 and week 4 of 100 items each and this item has a lead time of 1 week, when and how large of an order should be placed to meet the requirement of 300 items? O Week 4, 50 items Week 4, 300 items O Week 1, 300 items O Week 1, 40 items O Week 5, 60 items Moving to another question will save this response. isi Question 10 or 25 406 PM

Explanation / Answer

Current in stock = 50 units

Scheduled receipts in week 3 and week 4 = 200 units

Total stock = 50 + 200 = 250 units

Required stock in week 5 with 1 week lead time = 300 units

Hence 50 should be ordered in week 4.

Week 4, 50 items.