Safarl File Edit View History Bookmarks Develop Window Help ezto.mheducation.com 20.00 points PA 18-12 to 18-15 Processing times and due dates for five jobs... Processing times and due dates for five jobs are shown in the table below. Assume the jobs are processed using the earliest-due-date rule. Job Processing time (weeks) 3.00 0.40 1.10 4.00 1.50 Due date (weeks) A B C D E 3 5 5 6 3 12.What would be the lateness of job B? 13. What would be the tardiness of job E? 14. What is the average flow time for this set of jobs? 15. What is the maximum tardiness for this set of jobs? weeks (Round your answer to 2 decimal places.) Round your answer to 2 decimal places.) (Round your answer to 2 decimal places.) (Round your answer to 1 decimal place.) weeks weeks weeks B.

Explanation / Answer

Job Processing time Due Date A 3 3 B 0.4 5 C 1.1 5 D 4 6 E 1.5 3 The sequence of the jobs will be:- E,A,B,C,D The above table will be as below Job FLOW TIME DUE DATE LATENESS IN OUT EARLINESS TARDINESS E 0 1.5 3 -1.5 A 1.5 4.5 3 1.5 B 4.5 4.9 5 -0.1 C 4.9 6 5 1 D 6 10 6 4 LATENESS OF JOB B=-0.1 TARDINESS OF JOB E=1.5 AVERAGE FLOW TIME = (1.5+4.5+4.9+6+10)/5 = 5.38

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at drjack9650@gmail.com
Chat Now And Get Quote