An architect has five projects to complete. She estimates that three of the proj
ID: 376098 • Letter: A
Question
An architect has five projects to complete. She estimates that three of the projects will require 1 week to complete and the other two will require 3 weeks and 4 weeks. During the time these projects are completed, assume no other projects are worked on during this time. What is the architect’s flow rate? projects per week (Round your answer to 1 decimal place.) An architect has five projects to complete. She estimates that three of the projects will require 1 week to complete and the other two will require 3 weeks and 4 weeks. During the time these projects are completed, assume no other projects are worked on during this time. What is the architect’s flow rate? projects per week (Round your answer to 1 decimal place.)Explanation / Answer
time to complete (weeks)
project 1
1
project 2
1
project 3
1
project 4
3
project 5
4
10
Flow rate = throughput or the no. of units going through the process per time unit.
Little's Law, R=I/T
I is the inventory, or the no of units contained in the system
T is the time taken for all inventory to go through the process
R is the rate at which the process is delivering, or the flow rate
here,
I=
5
projects
T=
10
weeks
architect’s Flow rate, R=
0.5
projects/week
time to complete (weeks)
project 1
1
project 2
1
project 3
1
project 4
3
project 5
4
10
Flow rate = throughput or the no. of units going through the process per time unit.
Little's Law, R=I/T
I is the inventory, or the no of units contained in the system
T is the time taken for all inventory to go through the process
R is the rate at which the process is delivering, or the flow rate
here,
I=
5
projects
T=
10
weeks
architect’s Flow rate, R=
0.5
projects/week
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.