22. Activity A has a start-to-start relationship with Activity B, with a three-d
ID: 372298 • Letter: 2
Question
22. Activity A has a start-to-start relationship with Activity B, with a three-day lag. If A's duration is ten days and B's duration is six days, what is the total amount of time it will tke to complete both A and B activities? b. c. d. e. 10 days 12 days 16 days 19 days there is not enough information 23. For a large project, the appropriate time to introduce the project and get team buy-in on the project management plan is: a. at the end of the project planning phase b. after the baselines are set c. at the kick-off meeting d. after the project charter is signed e. none of the above 24. In staffing negotiations with the line manager, you identify a work package that requires a skill set of a grade 7 worker. The line manager informs you that she will assign a grade 6 and a grade 8 worker. a. refuse to accept the grade 6 because you are not responsible for training b. ask for two different workers c. be happy! You have two workers d. ask the sponsor to interfere e. ask the project manager to intervene You should: 25. Project management is accomplished through the appropriate application and integration of how many logically grouped project management processes? a. 40 b. 5 c. 12 d. 47 e. 10 26. In your interview a functional manager who says: We have this huge undertaking of launching an on-line education website that contains different components. Each component is functionally complex and arge enough and be better served under a different management. The manager is most likely describing a/an: a. project b. program e. operation d. portfolio e a&b; 27. A project has the following network diagram. Determine the critical path. a. Start-A-B-C-D-End b. Start-E-B-C-D-End c. Start-E-F-H-End d. Start-E-G-H-End e. None of the above 28. You work for a state agency that sets up literacy programs for ec economically challenged counties and cities Which of the following is not a criterion that your agency would use when selecting projects? a. Strategic alignment b. Nonfinancial benefits Riskiness of the project Financial benefits a and c c. d. e.Explanation / Answer
22. Start-to-start relationship, Activity B must start after 3 days of Activity A starts
Suppose Activity A starts at day 1 and it takes 10 days to finish then it will finish on day 10
And activity B will start with 3-days lag at day 4 and it takes 6 days to finish so it will finish on day 9
Therefore total time required to finish both Activity A and activity B is 10 days
Therefore correct answer is option a. 10 days
23. For a large project, the appropriate time to introduce the project and get team to buy-in on project management plan is at the kick-off meeting.
Therefore correct answer is option c. at the kick-off meeting.
The kick-off meeting is the right time where the team is introduced to project and project management plan.
24. In staffing negotiations with the line manager, you identify a work package that requires a skill set of a grade 7 workers. The line manger informs you that he will assign a grade 6 and a grade 8 worker. You should be happy! You have two workers.
Therefore correct answer is option c. be happy! You have two workers
Because may be there is non-availability of a worker with skill set of a grade 7 therefore the line manger informs you that he will assign a grade 6 and a grade 8 worker.
25. Project management is accomplished through the appropriate application and integration of how many logically grouped project management processed
Project management is accomplished through the appropriate application and integration of the 47 logically grouped project management processes.
Therefore correct answer is option d. 47
These 47 logically grouped project management processes are further categorized into five process groups which are initiating, planning, executing, monitoring and controlling, and finally closing.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.