Question 23 (2 points) The baseline project plan (BPP) is the primary deliverable from the project identification and selection phase. True O False Save Question 24 (2 points) Meeting notes, procedure manuals, and consultant reports are specific deliverables that might be obtained during the requirements determination process 0 True .5 False 30 Save 35 Question 25 (2 points) As a general guideline, you should prepare an agenda with approximate time limits for different sections of the interview. O True False SaveExplanation / Answer
Solution:
23)
True
Explanation:
Because the baseline decides how the project will perform so it is important do from project identification and selection phase.
24)
True
25)
True.
I hope this helps if you find any problem. Please comment below. Don't forget to give a thumbs up if you liked it. :)
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.