A job completion time follows a triangular distribution and can be accurately es
ID: 368725 • Letter: A
Question
A job completion time follows a triangular distribution and can be accurately estimated for the project manager. The most likely completion time is 10 days (m), the most optimistic estimate of completiontime is 5 days (a), while the most pessimistic estimate is at 18 days (b).
C1: Compute the Expected completion time for this job:
C2: Compute the variance for this job:
C3: Determine the probability of completing the job between 3-8 days.
C4: The vendor earns $1,000 for a job completed within 8 days, but loses $250 for any job completed after 8 days. Compute the expected profit/loss for the vendor performing the same job 1000 times.
Explanation / Answer
Expected completion time for the job
= ( Optimistic completion time + 4 x Most likely completion time + Pessimistic completion time ) / 6
= ( 5 + 4 x 10 + 18 )/ 6
= 63/6
= 10.5
Standard deviation of completion time for the job
= ( Pessimistic completion time – Optimistic Completion time ) / 6
= ( 18 – 5 ) / 6
= 13/6
Therefore, Variance for the job
= ( Standard deviation for the job)^2
= ( 13/6)^2
= 4.694
EXPECTED COMPLETION TIME FOR THIS JOB = 10.5 DAYS
VARIANCE FOR THIS JOB = 4.694 DAYS
Let Z value corresponding to probability of completing the job in 3 days = Z1
Let Z value corresponding to probability of completing the job in 8 days = Z2
Hence,
Expected completion time + Z1 x standard deviation of completion time = 3
Or, 10.5 + 13/6 x Z1 = 3
Or, 13/6x Z1 = - 7.5
Or, Z1 = - 3.46
Probability corresponding to Z1 = - 3.46 as derived from standard normal distribution table= 0.00027
Similarly,
Expected completion time + Z2 x Standard deviation of completion time = 8
Or, 10.5 + Z2 x 13/6 = 8
Or, 13/6 x Z2 = - 2.5
Or, Z2 = - 1.15
Probability corresponding to Z2 = - 1.15 as derived from standard normal distribution table= 0.12507
Thus probability of completing the job between 3 – 8 days
= probability of completing the job in 8 days – Probability of completing the job in 3 days
= 0.12507 – 0.00027
= 0.1248
PROBABILITY OF COMPLETING THE JOB BETWEEN 3 TO 8 DAYS = 0.1248
Probability of completing a job within 8 days = 0.12507
Thus, probability of completing the job after 8 days = 1 – 0.12507 = 0.87493
Expected earning for completing the job within 8 days = $1000 x 0.12507 = $125.07
Expected loss for completing the job after 8 days = $250 x 0.87493 = 218.73
Thus, Net expected loss for performing the job once = $218.73 - $125.07 = $93.66
Hence, Expected loss for vendor performing the same job 1000 times = $93.66 x 1000 = $93660
EXPECTED LOSS FOR THE VENDOR PERFORMING THE SAME JOB 1000 TIMES = $93660
EXPECTED COMPLETION TIME FOR THIS JOB = 10.5 DAYS
VARIANCE FOR THIS JOB = 4.694 DAYS
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.