A project has two paths that you are concerned about. The first path (which we w
ID: 366357 • Letter: A
Question
A project has two paths that you are concerned about. The first path (which we will call #1) has an expected path time of 15 weeks and a standard deviation of 3. The second path (#2) has an expected path time of 14 weeks and a standard deviation of 3.4. Which path is critical if the project must be completed within 16 weeks? Path #2 is critical with a probability of approximately 63% O Path #2 is critical with a probability of approximately 72% O Path #1 is critical with a probability of approximately 63% O Path #1 is critical with a probability of approximately .333 Path #1 is critical with a probability of approximately 73% Path #1 is critical with a probability of approximately .588Explanation / Answer
Path #2 is critical probablity of approx 72%.
Please leave a comment if you want an explanation.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.