You work for a landscaping company. You need four poles and 2 cubic yards of mul
ID: 359023 • Letter: Y
Question
You work for a landscaping company.
You need four poles and 2 cubic yards of mulch for every tree that is planted.
Calculate the Material Requirements Plan below.
The beginning inventory for each item has been given.
Week
Beg. Inv.
1
2
3
4
5
6
7
8
Quantity
72
65
30
64
Tree
Lead Time = 1 wk
Lot for Lot
Gross Requirements
Scheduled Receipts
Projected On-Hand
2
Net Requirements
Planned Order Receipts
Planned Order Releases
Poles
Lead Time = 1 wk
Lot Size of 12
Gross Requirements
Scheduled Receipts
Projected On-Hand
14
Net Requirements
Planned Order Receipts
Planned Order Releases
Mulch
(in cubic yards)
Lead Time = 1 wk
Lot-Size of 9
Gross Requirements
Scheduled Receipts
Projected On-Hand
9
Net Requirements
Planned Order Receipts
Planned Order Releases
Week
Beg. Inv.
1
2
3
4
5
6
7
8
Quantity
72
65
30
64
Tree
Lead Time = 1 wk
Lot for Lot
Gross Requirements
Scheduled Receipts
Projected On-Hand
2
Net Requirements
Planned Order Receipts
Planned Order Releases
Poles
Lead Time = 1 wk
Lot Size of 12
Gross Requirements
Scheduled Receipts
Projected On-Hand
14
Net Requirements
Planned Order Receipts
Planned Order Releases
Mulch
(in cubic yards)
Lead Time = 1 wk
Lot-Size of 9
Gross Requirements
Scheduled Receipts
Projected On-Hand
9
Net Requirements
Planned Order Receipts
Planned Order Releases
Explanation / Answer
Note that for Poles and Mulch, the PORs are multiples of 12 and 9 respectively just above the Net requirement.
Beg. Inv. 1 2 3 4 5 6 7 8 Quantity 72 65 30 64 Tree Gross Requirements 72 65 0 30 0 64 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On-Hand 2 2 2 0 0 0 0 0 0 Lead Time = 1 wk Net Requirements 0 0 70 65 0 30 0 64 Planned Order Receipts 0 0 70 65 0 30 0 64 Lot for Lot Planned Order Releases 0 70 65 0 30 0 64 0 Poles Gross Requirements 0 280 260 0 120 0 256 0 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On-Hand 14 14 10 2 2 2 2 10 10 Lead Time = 1 wk Net Requirements 0 266 250 0 118 0 254 0 Planned Order Receipts 0 276 252 0 120 0 264 0 Lot Size of 12 Planned Order Releases 276 252 0 120 0 264 0 0 Mulch Gross Requirements 0 140 130 0 60 0 128 0 Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On-Hand 9 9 4 9 9 3 3 1 1 Lead Time = 1 wk Net Requirements 0 131 126 0 51 0 125 0 Planned Order Receipts 0 135 135 0 54 0 126 0 Lot-Size of 9 Planned Order Releases 135 135 0 54 0 126 0 0Related Questions