You work for a landscaping company. You need four poles and 2 cubic yards of mul

ID: 357785 • Letter: Y

Question

You work for a landscaping company.

You need four poles and 2 cubic yards of mulch for every tree that is planted.

Calculate the Material Requirements Plan below.

The beginning inventory for each item has been given.

Week

Beg. Inv.

1

2

3

4

5

6

7

8

Quantity

72

65

30

64

Tree

Lead Time = 1 wk

Lot for Lot

Gross Requirements

Scheduled Receipts

Projected On-Hand

2

Net Requirements

Planned Order Receipts

Planned Order Releases

Poles

Lead Time = 1 wk

Lot Size of 12

Gross Requirements

Scheduled Receipts

Projected On-Hand

14

Net Requirements

Planned Order Receipts

Planned Order Releases

Mulch

(in cubic yards)

Lead Time = 1 wk

Lot-Size of 9

Gross Requirements

Scheduled Receipts

Projected On-Hand

9

Net Requirements

Planned Order Receipts

Planned Order Releases

Week

Beg. Inv.

1

2

3

4

5

6

7

8

Quantity

72

65

30

64

Tree

Lead Time = 1 wk

Lot for Lot

Gross Requirements

Scheduled Receipts

Projected On-Hand

2

Net Requirements

Planned Order Receipts

Planned Order Releases

Poles

Lead Time = 1 wk

Lot Size of 12

Gross Requirements

Scheduled Receipts

Projected On-Hand

14

Net Requirements

Planned Order Receipts

Planned Order Releases

Mulch

(in cubic yards)

Lead Time = 1 wk

Lot-Size of 9

Gross Requirements

Scheduled Receipts

Projected On-Hand

9

Net Requirements

Planned Order Receipts

Planned Order Releases

Explanation / Answer

Week Beg. Inv. 1 2 3 4 5 6 7 8 Quantity 72 65 30 64 Tree Gross Requirements 0 0 72 65 0 30 0 64 Lead Time = 1 wk Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On-Hand 2 2 2 0 0 0 0 0 0 Net Requirements 0 70 65 0 30 0 64 0 Planned Order Receipts 0 70 65 0 30 0 64 0 Lot for Lot Planned Order Releases 0 0 72 65 0 30 0 64 Poles Gross Requirements 0 280 260 0 120 0 256 0 Lead Time = 1 wk Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On-Hand 14 14 10 2 2 2 2 10 10 Net Requirements 266 250 0 118 0 254 0 0 Planned Order Receipts 276 252 0 120 0 264 0 0 Lot Size of 12 Planned Order Releases 0 280 260 0 120 0 256 0 Mulch Gross Requirements 0 140 130 0 60 0 128 0 (in cubic yards) Lead Time = 1 wk Scheduled Receipts 0 0 0 0 0 0 0 0 Projected On-Hand 9 9 4 0 0 3 3 1 1 Net Requirements 131 126 0 60 0 125 0 0 Planned Order Receipts 135 126 0 63 0 126 0 0 Lot-Size of 9 Planned Order Releases 0 140 130 0 60 0 128 0