Processing time of a set of servers is 18 minutes. T_p=18 minutes. There are 3 s
ID: 3576679 • Letter: P
Question
Processing time of a set of servers is 18 minutes. T_p=18 minutes. There are 3 servers. Utilization of these servers is 0.75 Compute the processing rate of this system R_p=? around 14.3 per hour around 18 per hour around 20 per hour around 10 per hour around 12 per hour Mark 1.00 out of 1.00 The correct answer is: d. around 10 per hour On average how many flow units are in these servers? I_p=? around 1 5 around 2.3 around 2 around 3 4 around 5 Compute the arrival rate (throughput) of this system. R=? around 9.3 per hour around 9 per hour around 8 3 per hour around 7.5 per hour around 6.3 per hour Mark 1.00 out of 1.00 The correct answer is: d around 7.5 per hour What is the average interarival time between two consecutive customers? around 9 minutes around 8 8 minutes around 8 minutes around 6.4 minutes around 5 minutes Mark 1.00 out of 1.00Explanation / Answer
Answers:
1. d. around 10 per hour
2. b. around 2.3
3. d. around 7.5 per hour
4. c. around 8 minutes.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.